Our guys have been busy this clearing the site for the diversion dam at 'Back Valley' on the river that we will be diverting part of the water from to supplement the flow at the intake dam for the penstock. They also cleared the path from the intake dam down to the site of the turbine house. That's two km so a lot of work to do with a cutlass. Fortunately, we had a good number working on the clearing and they finished today. Attached are some pictures of the sites.
Clearing the area for the canal from the diversion dam
Penstock trench from the intake dam to the edge of the escarpment
Penstock path from the escarpment to the turbine site
Cutting eucalyptus poles for the high-tension power line
How I wish I could be there for a few weeks or months. D.Lemke
ReplyDelete