Friday, December 4, 2020

Intake dam is complete

The intake dam is complete and the lake is full.  We have flushed out a lot of debris
so the water is clean.
This is the back side of the dam with water flowing through the spillway

The pipe welders are at work joining the 6 M pipes together.  The 12 M lengths 
will be moved into the penstock trench and welded together.  

We are preparing 1 M sections of conduit that will be installed in a trench that 
allows us to move water from the diversion dam into the front water shed
where it will flow into into the intake dam lake.  
200 




Saturday, November 14, 2020

We are making very good progress with the hydroelectric project.  We have now completed the intake dam and the generator house.  This week we will begin installing the penstock pipe and constructing the turbine house.  We will begin work on the diversion dam soon.  We will soon finish the funds that we have on hand for the project.  The total cost of the project is about $1.7 million.  We need to raise the last 10% of the budget.  If you are interested in supporting the project you may contribute at this link:  https://nabconference.org/give/special-projects/   Scroll down to the Hydroelectric Project in the Cameroon section.  We will appreciate your support.  


The intake dam is completed.  It was built in four months.  

The guys are cementing in the shutter gate that can be raised to drain the lake.  This was the last step in completing the dam.  The gate weighs about a ton but they were able to manually lift it into place.  The crane that we were planning to use is broken.  We are at the beginning of the dry season so the amount of water in front of the dam is very low.  


This is the site for the turbine house.  It sits just across a ravine that will need to be filled with dirt.  At the edge is 2X5 M stone wall that will anchor the penstock.  There is very high lateral pressure on the penstock so that it must be anchored very firmly to prevent movement.  The penstock goes through the stone wall and directly into the turbine.  



This shows the ravine.  We have placed a 1 M culvert at the bottom to drain the small stream that runs along the bottom.  



In order to move water from the diversion dam into the front watershed, we will place a 1 M culvert through a 100 M wide ridge.  We will need to dig down about 8 meters.  In order to save money, we are going to fabricate 200 of these concrete rings.  These will be placed at the bottom of the trench and buried.  This is a homemade form that our guys made.  

Tuesday, October 20, 2020

The intake dam is nearing completion.  A top cap 
concrete is most of what remains. 

Back side of the dam.  

This is how we generally get work done here.  


Lifting penstock pipe is much easier with the Bobcat

Turbine house is nearly completed.  Waiting for the 
big diesel generator to be installed.  

                                       

Saturday, August 29, 2020

The work on the project is focused on the construction of the intake dam. 
We  are making good progress and hope to have it completed in 3-4 weeks 


Each of the steps on the back of the dam is 1/2 meter wide and high. 
There are 10 steps in total.  

















 


 
      We successfully moved all of the crates containing the turbine and
other components of the hydro system up to the hospital.  













  The bobcat has proven to be indispensable for the project.

Sunday, August 9, 2020

The diesel generator house is nearing completion.  This building will house the two generators and the electrical switching equipment.  The hospital will have three power sources when the project is completed, the hydroelectric system, diesel generators and the national power grid. 

This is the 11 inch penstock pipe that will carry the water from intake dam up on the hill, 2 km down to the turbine.  It will deliver 100 L of water/sec at full power.  

Work on the dam is progressing well.  The far end of the dam is at the final height.  Each step is 0.5 meter.  The base of the dam will be 7 meters at it's widest.  A steel shutter will be placed in the dam where the steps end that can be opened allowing the dam to be drained. 

This is the dam viewed from the north end. 

 The opening in the dam is for the penstock to pass through.  There will be two penstock attachments and one 4 inch water pipe connected.  A rake and coranda will be installed on the lake side of the dam to collect debris and prevent it from entering the penstock.  

 

Saturday, July 4, 2020

Hydro Update


Work is progressing on the hydro project.  Lots of prep work to be done before the actual construction of the components begins.  

We are upgrading the roads to the turbine house and up to the intake dam site. 
The bobcat with the dozer blade works well for this.  
Things are progressing quickly on the generator house.  The pillars for the
roof will be up shortly and we will pour the cement floor.  We hope to
 have it completed in three weeks or so.  
This is the penstock pipe track.  It is two km long running from the intake
 dam to the turbine house.  Digging of the track has been finished.  
The work to build the intake dam began this week.  Pipes were place in the
stream bed to allow the flow from the stream to pass through the dam.  These
pipes will be sealed after the dam is completed.  A large steel shutter
will be built into the dam to allow the lake to be drained for cleaning when needed.  
This is the stone quarry where the stones for the dam are dug and shaped. 
They are moved a few hundred meters to the dam site.   
The unimog is used to carry the stones up to the dam site. 

Monday, June 8, 2020

 We don't have a crane to do the heavy lifting but we do have a lot of strong backs and willing hands.  The guys were moving the high-tension poles up onto the road - one foot at at time.  Took a little while but they got the job done.  There are forty of the poles. 














Another crew moved concrete rings down into a ravine to form a culvert.  This is a ravine next to the turbine house and has a small stream at the bottom.  They lowered the rings with ropes one at a time then rolled them into place.  We will back fill over the rings making a bridge that our equipment can pass over to work on the penstock route.