The work on the project is focused on the construction of the intake dam. 
We  are making good progress and hope to have it completed in 3-4 weeks 


Each of the steps on the back of the dam is 1/2 meter wide and high. 
There are 10 steps in total.  

















 


 
      We successfully moved all of the crates containing the turbine and
other components of the hydro system up to the hospital.  













  The bobcat has proven to be indispensable for the project.