Saturday, August 29, 2020

The work on the project is focused on the construction of the intake dam. 
We  are making good progress and hope to have it completed in 3-4 weeks 


Each of the steps on the back of the dam is 1/2 meter wide and high. 
There are 10 steps in total.  

















 


 
      We successfully moved all of the crates containing the turbine and
other components of the hydro system up to the hospital.  













  The bobcat has proven to be indispensable for the project.

Sunday, August 9, 2020

The diesel generator house is nearing completion.  This building will house the two generators and the electrical switching equipment.  The hospital will have three power sources when the project is completed, the hydroelectric system, diesel generators and the national power grid. 

This is the 11 inch penstock pipe that will carry the water from intake dam up on the hill, 2 km down to the turbine.  It will deliver 100 L of water/sec at full power.  

Work on the dam is progressing well.  The far end of the dam is at the final height.  Each step is 0.5 meter.  The base of the dam will be 7 meters at it's widest.  A steel shutter will be placed in the dam where the steps end that can be opened allowing the dam to be drained. 

This is the dam viewed from the north end. 

 The opening in the dam is for the penstock to pass through.  There will be two penstock attachments and one 4 inch water pipe connected.  A rake and coranda will be installed on the lake side of the dam to collect debris and prevent it from entering the penstock.